endecsbgat

Project for a industrial, medical and specialty gases and gas equipment

25Apr

We worked for one of the leading suppliers of industrial, medical and specialty gases and gas equipment in Czech Republic. ACS worked here on Upgrade of cooling towers project, we were responsible for complete cabling reinstallation, manufacturing and switchboard installation. We replaced the local control boxes with IOP-2 FM touch screens and install the cabels for control system. ACS also installed and supplyied two motors with frequency converters. During the test operation, we performed a preventive check of the temperature conditions in the switchboard with a thermal camera.

This site is registered on wpml.org as a development site.