The scope of supply for the project includes the engineering, delivery, installation and commissioning of the fluidised bed boiler, including flue gas cleaning system with high-dust SCR. The equipment and technologies supplied by the customer are essential components of a highly efficient biomass power plant for feeding green energy into the national grid. The biomass power plant, which will run on palm kernel shells and wood pellets, will generate about 50 MW of electricity, providing clean energy from renewable sources to about 100,000 households.

ACS is responsible for the electrical and I&C systems as well as commissioning. The scope of work thus includes electrical and logical control and modification, protection control, modification of cabling, machine control, control of mechanical parts and much more. The project is now in the transition phase from cold commissioning to hot commissioning